Transports show wrong cost

Works as intended UI & UX
prometheus0000 [discord] · 1 year ago

They all say 28. T2 has slightly different numbers, for the increased rubber cost. Presumably it'd be the same for T3. It's like this for pipes and molten channels as well. Dunno about train tracks, as I don't have them yet.

When placing, you can tell obviously it's not 28. If you wanted to show cost per 28 tiles or something, it should say that.

image.jpg
image.jpg

Captain Marek Captain Marek · 1 year ago

This is cost per 100 tiles, is it not right?

prometheus0000 [discord] · 1 year ago

I can't check right now if it's accurate, but in that case the issue is that it doesn't indicate it's per 100 tiles, or that it can be higher/lower. I would read it as 28 CP per tile.

Captain Filip Captain Filip · 1 year ago

Those numbers seem correct per 100 tiles 👍🏻 Though I agree we could be clearer that it's per 100, so will add that as a separate issue

Closed as ☑️ Works as intended

6 Showing 1–4 of 4